San Jose residents went to City Hall this week asking for an emergency halt on new data centers. They left with a promise that future projects will have to fund parks and affordable housing — and no pause at all.
At the Rules and Open Government Committee on Aug. 13, the city answered a growing call for a moratorium the way it has answered nearly every data-center fight this year: with process. Councilmembers directed staff to fold community-benefit requirements into the standards already being written for a December council vote, and to study steering some data-center tax revenue back into surrounding neighborhoods. What they did not do is stop accepting applications — leaving intact the exact window that critics say rewards developers who file now and lock in today's looser rules before any new ones bind them.
The Dissent reported last week that San Jose is spending until December writing data-center rules while it keeps approving data centers. This week the city acted — but on the developers' obligations, not on the pipeline residents wanted frozen.
The distinction matters because of what's already in motion. Roughly 20 data centers operate in San Jose, six are under construction, and five more are working through city approvals, according to figures the City Manager's Office gave San José Spotlight. Every one of those five could clear review under the current code — before the uniform standards on water, power, air quality, noise and emissions reach the council in December.
That timing is the whole fight. In a letter to councilmembers, Alice Kaufman, policy and advocacy director for the environmental group Green Foothills, argued that writing rules without pausing intake creates a "perverse incentive": developers racing to file now so their projects are locked into today's weaker requirements, per Spotlight's account. She was not alone. At the committee hearing, Lena Drape of the Santa Clara Valley Open Space Authority pressed the city to freeze new applications until the standards are adopted, warning of a "reverse incentive" that rewards a scramble to beat the deadline, KQED reported (external source, opens in a new tab).
Alviso advocate Mark Espinoza told Spotlight the process shouldn't be rushed, and urged the council to "listen to the community" that will end up as the data centers' nearest neighbors.
Two advocates, two organizations, one warning: the delay itself is the loophole. San Jose has watched other jurisdictions — New York state and Oakley, California among them — enact outright moratoriums, and residents keep asking why it hasn't followed.
The city's answer is that the math doesn't support the fear. Officials note that a special-use permit alone takes more than six months, and projects requiring environmental impact reports run far longer, so an application filed today is unlikely to beat the December standards to the finish line. District 4 Councilmember David Cohen, a backer of the standards effort, went further, telling Spotlight the industry isn't the adversary: developers, he said, want the cleanest technology available, and the city has already been pressing them to build to whatever the rules will eventually demand.
Whether that informal ask has teeth is precisely what a moratorium would settle — and what the committee left unsettled. San José Spotlight reported that one proposal advanced Wednesday would direct staff to reevaluate pipeline projects once the standards exist and reopen development agreements that fall short, with a city spokesperson vowing to pull as many in-progress projects as possible under the new rules. KQED, covering the same meeting, described the committee's action more narrowly — folding in community benefits and studying tax reinvestment — and did not report any vote to renegotiate existing agreements. The gap between those two accounts is the gap residents are worried about.
For the people who live beside the sites, the community-benefits win reads as beside the point. Alviso advocate Mark Espinoza told Spotlight the process shouldn't be rushed, and urged the council to "listen to the community" that will end up as the data centers' nearest neighbors.
The city's first public listening session is set for Aug. 19 at City Hall. The standards — and the unanswered question of what happens to everything already in the pipeline — are due back before the council in December.